⏳ V2 Platform Camper orders placed today will be completed in February, just 20 weeks from now. This is regularly updated to reflect the most accurate lead times. ⚡️

0

Your Cart is Empty

SUPERLITE LEADERBOARD

July 02, 2021 1 min read

ESTIMATED PRODUCT ARRIVAL TIMES ARE SUBJECT TO CHANGE FROM CURRENTLY DISPLAYED DATES, BUT UPDATES WILL BE POSTED HERE IN REAL TIME.

___________________________

CURRENT STATUS: Week of 9/13/2021

30 SuperLites were built last week. 30 Units anticipated this week with an intended ramp up to 60 as soon as possible as we are hiring more staff. All materials needed are currently on hand.

___________________________

COMPLETED BATCH 1

-Batch 1 is the first 576 units built.

BATCH 2

-Batch 2 is a 400 unit build batch that was waiting for tent fabric. The fabric arrived on 7/21/21. Honeycomb panels, extrusion and other build materials are currently in inventory, so all materials are now in hand. This is not your build date, it is the anticipated date the block has all materials required for production.

 

BATCH 3

-Batch 3 is a 360 unit build batch with fabric currently scheduled to arrive 9/1/21. We have partial supply of honeycomb panels and poles to begin the block, about 50 units, and resupply of those materials are anticipated to arrive the weeks of 9/1/21-9/13/21. This is not your build date, it is the anticipated date the block has all materials required for production.

BATCH 4

-Batch 4 is a 153 unit build batch with honeycomb panels currently scheduled to arrive the week of 9/27/21. Fabric is anticipated to arrive 11/1/21.

This is not your build date, it is the anticipated date the block has all materials required for production.

Fulfillment GFC